DESCRIPTION
In Gdynia linkspan was loaded by floating crane onto barge GDY-20/21 with prepared supports on which it was transported to Ullapool. Our crew was sent to Ullapool to discharge the linkspan.
Term: Gdynia Aprill 2015/ Ullapool May 2015
The scope of work was divided in following steps:
- - Preparation of the CW4 barge for installation
- - Moving of the linkspan from GDY21 barge to CW4 barge (skidding operation)
- - Installation of the linkspan (float over operation)