DESCRIPTION
Skidding of Condenser (Q=550T) from assembly site to the Machinery Hall in new-built Power Plant in Turów (Bogatynia). Due to high level difference between assembly site and basement of Machinery Hall (4,5m), skidding rail were supported by number of high steel supports (h=4,5m). After skidding, all skidding substructure had do be removed from underneath of Condenser. Then Condenser was jacked down abt. 1,2m and settled onto prepared foundation with tolerance of +/-1mm. For jacking operation Trend used 4 pcs. of Climbing Jacks (CLJ160) with capacity 160t each.